From concept to completion in 20 months.
A clear plan, one partner, no surprises.
Assessment
1 month
Planning Your Project
We'll assess your property, discuss your needs, and explore the possibilities together. From there, we’ll provide a clear cost estimate tailored to your goals.
Key Activities
- Needs Assesment
- Project Outline
- Estimate
Duration
1-4 week
Design & Permitting
9 - 12 months
Home Design
We’ll order a land survey and bring in any required consultants for your property and region. Once we've done the groundwork, you’ll sit down with your designer for a needs assessment to explore your lifestyle, preferences, and goals. From there, we’ll present design options tailored to reflect your vision and requirements.
Key Activities
- Site Plan
- Sections
- Elevations
Duration
4-7 months
Permit
We’ll take care of all the permits, utilities, and city requirements, handling everything from preparation to submission to make the approval process as smooth as possible.
Duration
3 to 4 months with Municipality
Finish Selection
While we wait for permits, we’ll begin to bring your home to life–working with you to choose fixtures and finishes from our catalogue of timeless and tested standard finishes, and designing custom millwork that reflects your needs and style.
Key Activities
- Select Finishes & Fixtures
- Custom Millwork
Duration
Concurrent with Permitting
Budget
With the final design complete, we’ll provide a fixed-price budget tailored to your selections, reflecting any upgrades. This meeting is like the checkout—where we make decisions on what’s included or adjusted.
Key Activities
- Budget Presentation
- Construction Agreement
Duration
1 month
Construction
7 to 9 months
Groundbreak
With everything in place, we’ll start building your home. Our site supervisor will be in touch regularly to keep you updated on progress and schedules.
Key Activities
- Demolition
- Excavation
- Foundation
- Framing
- Services
- Doors & Windows
Duration
3 months
Lock-up
Your home’s structure is now fully enclosed, with the roof, windows, and doors installed. This secures the building and protects it from the elements.
Finishing
It's time for the home to come together. At this stage, you will start seeing all of the wonderful finishes and millwork you selected and your Smallworks house will transform into a home.
Key Activities
- Insulation
- Drywall
- Flooring
- Millwork
- Tile
- Paint
- Landscaping
- Inspection
Duration
4 to 6 months
Completion
20 months total
Hand-off
After thorough inspections, we’ll address any deficiencies to ensure everything meets our standards and yours. Once your home is move-in ready, we’ll give you a personal tour, review your home warranty, and hand over the keys.
Key Activities
- Walkthrough
- Address Deficiencies
- Key Hand-Off
- Warranty Commences
Move in
Your new dwelling is complete. It’s time for you or your guests to move in and make it a home.